Jefferson County: roof permit rules and hail requirements
Jefferson County Building Safety
Unincorporated Jefferson County moved to the 2024 Jefferson County Building Code for permits filed on or after July 1, 2026. Roof repairs under 25% of the roof and no more than two squares are permit-exempt; everything else is permitted, tear-off only (no overlays), with a mandatory mid-roof inspection at 10-25% complete — photo documentation not accepted.
| Code edition | 2024 Jefferson County Building Code for permits applied for on or after July 1, 2026 — one of four surveyed jurisdictions that changed codes in mid-2026. |
|---|---|
| Permit | Repairs under 25% of the total roof area and not more than two squares (200 sq ft) are exempt. Each separate structure — detached garage, shed — needs its own permit. |
| Tear-off & materials | One layer of asphalt shingles only, no overlays. Drip edge at eaves and gables; ice barrier required for asphalt shingles and most steep-slope coverings; wind resistance per ASTM D7158 (G or H) or D3161 (A, D, F). |
| Inspections | Mid-roof inspection required at 10-25% complete, plus final. Photo documentation is not accepted — an inspector visits. Class A assemblies required in the wildland-urban interface overlay. |
Details to confirm with the county
We couldn't confirm the following from Jefferson County's official pages. Check these with the county before you rely on them:
- Lakewood, Arvada, Golden, and other incorporated cities permit through their own building departments — their rules differ.
Verified July 2026 · Source: Jeffco Building Safety — Important Notice on Roofing (July 1, 2026)